Technology · Power distribution
Power distribution in the AI data center
Distribution stages from the grid connection to the GPU rack, redundancy architectures and the dynamics of training load. Wattality's products are designed to work at specific stages of this chain.
Distribution stages
From the grid connection to the GPU rack
Drawn topology: 2N distribution, A side and B side. Cooling loads on a side branch from side B.
01 / 07Grid connection
01Stage
Grid connection
- Function
- Point of interconnection and main transformers. Two independent medium-voltage (MV) feeds.
- Risk
- Fast load changes appear at the point of connection. Interconnection terms can limit ramp rate and oscillation.
- Data gap
- Meters record averages. Second-level load and IT activity are not in one record.
- Wattality
- Site is designed to run grid, generators and batteries as one system.
02Stage
MV switchgear, A and B sides
- Function
- Each side is sized for the full critical load. Generators connect at the MV bus.
- Risk
- A shared bus, breaker, cable route or room ties both sides to one failure.
- Data gap
- Relay event records stay in the devices. Post-event sequencing is done by hand.
- Wattality
- Site is designed to track breaker states and generator readiness on one timeline, from outside the protection chain.
03Stage
MV uninterruptible power supply (UPS) and battery
UPS type
- Function
- Double conversion: the load is fed from the inverter, the battery sits on the DC link. Line-interactive: the load is fed from the source, the battery sits on a shunt converter.
- Risk
- End-of-life capacity is assumed with a fixed aging factor. Power capability is not measured in service.
- Data gap
- Cell internal resistance and chemical state. Monitoring usually stops at block or module voltage and temperature.
- Wattality
- Sense is being developed for cell-level measurement, Core for pack control and DC/DC for energy transfer between packs.
04Stage
MV/LV transformer
- Function
- Steps medium voltage down to the hall's low voltage (LV).
- Risk
- Harmonics and load cycling raise winding temperature. Winding temperature sets insulation life.
- Data gap
- Winding temperature stays in the transformer relay and is not logged on the load profile's clock.
- Wattality
- Site is designed to log transformer data on the same clock as the load profile.
05Stage
LV switchboard
- Function
- Hall and rack feeders. Protective device coordination between breakers.
- Risk
- If coordination is lost, a fault moves to the upstream breaker and more racks lose power.
- Data gap
- Feeder loads and trip records sit in power monitoring, on a separate clock.
- Wattality
- Site is designed to merge feeder data with UPS and battery data in one data model.
06Stage
Server rack: busway, PDU, PSU, BBU
- Function
- A and B busways, power distribution units (PDU), dual-corded server power supplies (PSU), in-rack battery backup unit (BBU).
- Risk
- GPU load moves in synchronized steps. The swing propagates up the chain.
- Data gap
- Power inside the rack changes within milliseconds. Upstream systems see averages over seconds.
- Wattality
- BBU is designed to meet fast load steps on the rack power line.
07Stage
Cooling and mechanical loads
- Function
- Chillers, pumps and coolant distribution units (CDU). Separate mechanical branch.
- Risk
- With liquid cooling, a stopped pump heats the GPUs quickly. Some pumps need uninterruptible supply.
- Data gap
- Mechanical power and IT load are not on one timeline.
- Wattality
- Site is designed to plan the order in which mechanical loads return after a source transfer.
Load dynamics
UPS type and the in-rack BBU set how much of a load step reaches the source.
In a training job the GPUs compute and wait in step. Hall load shows a start-up ramp, synchronized steps, checkpoint dips and abrupt stops.
BBU is designed to meet fast steps. Site is being developed to assign each change to a source.
UPS type
BBU at the rack
The swing travels up from below
Generator or grid
Slow ramp
UPS and its battery
Input ramp limited, difference from the battery
BBU in the rack
Takes the fastest steps
GPU load
Steps, dips, oscillation
The BBU meets the fastest steps inside the rack. The UPS limits how fast its input power changes and covers the difference from its battery. The source sees a slow ramp.
Redundancy architectures
N+1, 2N, distributed redundant and block redundant distribution
- Two sides are independent when they share no bus, breaker, cable route or room.
- A single-corded load hangs on one side; it reaches the second side only through a static transfer switch (STS).
- Site is designed to track whether each UPS and battery can carry the load it takes on after a single failure.
Architecture
State
2N, A and B sides
The two sides share the load. The PSUs draw from both feeds.
- Normal loading
- ≤ 50% per side.
- Single failure
- One side lost: dual-corded PSUs draw from the other side. No transfer.
- Concurrent maintainability
- A whole side can be taken out for maintenance.
- Batteries
- Each UPS has its own battery. The sides are separate.
Facility data
Four control systems, four separate clocks
The battery management system (BMS), the UPS controller, the electrical power monitoring system (EPMS) and the generator controls each log on their own clock and in their own format. Post-event sequencing is done by hand.
Site · supervisory layer
Setpoints and operating modes
Battery management (BMS)
Cells and modules
Own clock
Own data formatUPS controller
Rectifier, inverter, battery
Own clock
Own data formatPower monitoring (EPMS)
Meters, breakers, feeders
Own clock
Own data formatGenerator controls
Engine and regulators
Own clock
Own data format
Protection · trips and interlocks hardwired
Each system logs on its own clock. The same event appears at four different times in four records.
Site: one clock, one data model, outside the protection chain
Designed as a supervisory layer for setpoints and operating modes. It takes no part in trip decisions. Trips and interlocks stay hardwired.
Fleet is a separate cloud product that connects sites and develops the models.
Design
We design the power distribution architecture and redundancy structure for AI data centers and critical facilities.
- 01Power distribution architecture and redundancy topology (N+1, 2N, distributed redundant, block redundant)
- 02UPS and battery sizing
- 03Generator step-load and load-dynamics studies
- 04Short-circuit studies and protective device coordination
- 05Single-line diagrams
- 06Battery and facility control layer integration
- 07Commissioning support
Let's talk about your facility's power distribution.
Write to us about redundancy architecture, UPS and battery sizing or facility data.